Commercial · Prime office high-rise
The Bow Tower
Calgary, Alberta. Project Manager on the 58-storey, $1.4 billion office tower, a Calgary landmark and once the tallest building west of Chicago.
Location
Calgary, Alberta
Client / owner
EnCana Corporation
Our role
Project Manager
Budget
$1.4 billion
Completion
2012
Project overview
A 58-storey office tower, a Calgary landmark, named Calgary's Most Beautiful Building.
— At one point it was the tallest building west of Chicago.
— The Bow was the largest steel project ever built in Canada.
— The raft slab pour was the largest continuous building pour in Canadian history.
Our role and scope
Project management of the access flooring systems, mechanical and HVAC constructability review, and construction coordination.
Challenges and solutions
A major challenge was that the washroom facilities were a containerized application: preconstructed units flown into each floor by crane, then transferred into position. However, the designers did not account for hooking up the units once they were placed, leaving no room for trades to connect the plumbing and electrical. This had to be worked out on site to achieve a satisfactory completion.
The unique kidney shape of the building also created problems levelling the flooring system, as the floor plates would flex in opposing directions during moderate to high winds. This caused the floors to twist as the building swayed by as much as 10 metres in each direction at higher elevations. This problem was eventually reduced to a more comfortable environment when interior rooms and offices were installed, greatly dampening the sway and stiffening the overall building.
Some high-wind days resulted in a shutdown of construction activities at the higher elevations. The building eventually stiffened once the interior offices were built, which helped reduce the sway and twist.
Some trades reported severe motion sickness from working long days at the higher elevations while the building was moving so much.
Results
Successfully resolved the washroom mechanical and electrical hookups.
Developed accurate methods of levelling the flooring system and managing structural plate twist and flex at higher elevations.